PSA: check your load chart before the morning meeting, not after your first pick
Had a rough one Tuesday at the yard over in Garland. Went to lift a prefab stair section, figured it was around 4,800 lbs off the tag. Got it about 6 feet up and the LMI started squawking at me. Turned out my radius was longer than I eyeballed it, close to 42 feet instead of 35, and with the boom angle I was running I was right at the edge. Set it back down, pulled the chart, moved the truck two bays over, and it picked clean. Took 20 extra minutes but kept me inside the lines.
The part that bugs me is I have done that same pick layout a dozen times. Just got in a hurry because the super was pushing. Now I walk the chart every morning before anyone shows up, coffee in hand, no audience. Cheap habit.
Curious what you all do when a super pressures you to just get it done, do you hold the line or find a middle ground?